Karachi building collapse death toll reaches 15 after two bodies recovered
Rescue teams continued searching the rubble of the under-construction building on Sunday. One of the latest victims was identified as Muhammad Mufeed.

Two more bodies were recovered from the rubble of a collapsed under-construction building in Karachi on Sunday, taking the death toll to 15, Rescue 1122 said. The rescue operation continued for a fifth day as teams searched for people feared trapped beneath the debris.
Rescue 1122 identified one of the victims as Muhammad Mufeed, son of Ghamin Gul. Identification of the other body was under way, the service said. The collapse happened on November 25 at a six-storey building in the Administration Employees Housing Society. Around 30 labourers were reportedly inside when the structure gave way.
The rising toll has renewed attention on the building’s approved plans and construction. Initial findings cited by The Express Tribune indicated that approval covered a basement, ground floor and one additional storey, while six extra floors had allegedly been built. The circumstances of the collapse and any responsibility for it remain under investigation.
What is known about the construction
The building stood on a 600-square-yard plot and was approved in March 2026 for a basement, ground floor and one additional storey. The Express Tribune reported that it had reached seven storeys, with work on a seventh floor reportedly under way when it collapsed. Six extra floors had allegedly been added beyond the approved plan.
Police detained six people in connection with the case, including the contractor and structural engineer, while the Sindh Building Control Authority suspended six officials, according to The Express Tribune. The source did not identify those detained. The allegations have not been established in court.
Rescue and safety checks
Rescue teams used heavy machinery and specialised equipment to clear debris and look for survivors. One construction worker was pulled out alive on Friday after rescuers reached an unstable part of the structure, The Express Tribune said. Business Recorder also reported that two men had earlier been rescued alive after 55 hours, both injured.
The Sindh Building Control Authority sealed 12 other under-construction buildings in the neighbourhood and began checking their ownership records, construction documents and approvals, The Express Tribune reported. The authorities have not announced when the search operation will end or provided a final account of how many people were inside the building.
This report draws on information from The Express Tribune and Business Recorder.
Editorial checks passed Facts, figures and quotes checked against 2 sources